restriction
Huddersfield Narrow Canal: Stanley Dawson Lock No 1E → Booth Lock No 31E
Update : September 30 2026, 10:38 AM Works at Slaithwaite reservoir remain ongoing, with levels within the reservoir drawn down to enable these works to take place safely. As such, there is no water available to feed to the canal and enable navigation. This drawdown of the reservoir will stay in place until the works complete in Spring 2027, and therefore re-opening the navigation before this time is unlikely. We will provide further update on navigation as the works at the reservoir progress through the winter months. Original : May 29 2026, 10:41 AM Works taking place at Slaithwaite Reservoir have necessitated a drawdown of reservoir levels that has been ongoing for several months. With recent warm, dry weather and an increase in boat movement on the canal, we have insufficient water resources to maintain navigation for the long term on the lower section of the canal. From Monday 15th June 2026 navigation between Lock 1E and Lock 31E will close with these locks being padlocked closed. Whilst the closure is in effect passage will only be possible between Standedge Tunnel and Lock 31E. Anyone looking to transit through Standedge Tunnel from Diggle in the Northwest will only be permitted to do so with a return tunnel booking. Boats will be able to turn in the winding hole above Lock 31E. Should levels in Slaithwaite Reservoir improve enough to provide an opportunity to open a passage window then details of this will be communicated by way of an update to this notice.
restriction
Huddersfield Narrow Canal: Wool Road Lock No 24W
Update : November 3 2026, 10:21 AM Since our previous update, our specialist contractors are still awaiting delivery of the bridge structure to carry out repairs. Due to the bespoke nature of these parts and the manufacturing process involved, delivery times can be longer than usual. Once the materials have been received, the repair works will be scheduled and a time frame for the work will be shared. In the meantime, assisted passages through the lock are available daily between 10 am and 2 pm. We require a minimum of 24 hours' notice for weekday passages and 48 hours' notice for weekend passages. To arrange an assisted passage, please contact our Customer Support team via the following link: https://canalrivertrust.org.uk/contact-us We will provide a further update on or before Tuesday, 24 November 2026. Update : October 22 2026, 9:36 AM Following our last update, our specialist contractors are currently awaiting delivery of the replacement bridge structure required to complete the repairs. Once the structure has been received, a date for the repair works will be scheduled. In the meantime, assisted passages through the lock are available daily between 10 am and 2 pm. We require a minimum of 24 hours' notice for weekday passages and 48 hours' notice for weekend passages. To arrange an assisted passage, please contact our Customer Support team via the following link: https://canalrivertrust.org.uk/contact-us. We will provide a further update on or before Tuesday, 3 November. Update : October 13 2026, 1:37 PM Our specialist contractors have been delayed in carrying out repairs to the footbridge due to other high-priority works. However, following successful repairs to the paddle at Lock 29 W, assisted passages through Lock 24 W are now available between 10 am and 2 pm daily, with at least 24 hours notice for weekday passages and 48 hours notice for weekend passages. If you wish to book an assisted passage, please contact our Customer Support team using the following
Navigation closed
Huddersfield Narrow Canal: Pickle Lock No 22E → Old Bank Bridge No 45
A navigation closure is required to carry out replacement of the top and bottom gates
Navigation closed
Huddersfield Narrow Canal: Lock No 7W (Huddersfield Narrow Canal) → Stalybridge Lock No 4W
A navigation closure is required to carry out replacement of the top and bottom gates and repair works to the lock chamber
Navigation closed
Huddersfield Narrow Canal: Keith Jackson Lock No 18W → Roaches Lock No 15W
A navigation closure is required to enable refurbishment works to the head gate at Lock 16, along with the reconstruction of the ground paddle chamber.
Navigation closed
Huddersfield Narrow Canal: Dungebooth Lock No 22W → Wade Lock No 21W
A navigation closure is required to facilitate Leak repair works to an abandoned sluice.
Navigation closed
Huddersfield Narrow Canal: White Hill Lock No 29E
A navigation closure is required to carry out repair works to the forebay and paddle chamber