Staffordshire and Worcestershire Canal: Rodbaston Lock No 35
A navigation and towpath closure are required to facilitate a bottom gate replacement to lock 35.
46.9 miles
Longest boat
21.95m
Widest boat
2.13m
Deepest draught
0.99m
Tightest of 1 section on the Trust's “Staffordshire & Worcestershire Canal (narrow)” table
advisory
A navigation and towpath closure are required to facilitate a bottom gate replacement to lock 35.
Navigation closed
Update : September 7 2026, 8:58 AM Following a review of the planned works, the extent of the navigation closure has been reduced from that originally proposed. The navigation will now be closed from Bridge 85, Princefield Bridge, to Bridge 86, Penkridge Bridge, for the duration of the works
advisory
The navigation will be closed at Lock 11, Kinver Lock while our Reactive Response team carries out essential repairs. The top end offside paddle stand has snapped and requires attention. To enable the repairs to be undertaken safely, the team will install a portadam to isolate the affected area. The existing plank grooves are also damaged, so new grooves will be installed as part of the works. Unfortunately, boats will not be able to pass through the lock while these works are taking place. We apologise for the inconvenience and thank customers for their patience while our team completes these essential repairs.
Navigation closed
Update : November 20 2026, 2:00 PM Works at this location are nearing completion and the stoppage is expected to be removed ahead of the published end date, with completion anticipated by 27 November. Please note that navigation through the wider route will remain unavailable due to the ongoing closures at Locks 35 and 38, where works are continuing. We would like to thank you for your patience and understanding while these works are being carried out. Original : May 1 2026, 11:06 AM A navigation closure is required to carry out replacement of the top gate. The full flight will be closed so water levels can be controlled and the works carried out safely.
advisory
Update : October 29 2026, 10:28 AM The new card reader has yet to be dispatched and is still in manufacture, we have been advised by the supplier this can take up to 30 days. Once this has been received our pump contractor will then schedule in fitting and testing, apologies for the delay. We will update further once the reader is received and a date for fitting can be made. Update : October 23 2026, 9:27 AM Please note it is the pump-out only that is affected. The Elsan is still in use. Update : October 13 2026, 8:46 AM Upon attending to the damaged hose, our contractors were not able to test the pump out as the card reader appears to have been vandalised. A new card reader will need to be ordered and then once this has arrived our contractors will schedule in reattendance for fitting and testing. We are not able to advise a time frame at present but will update further in due course.
advisory
Update : November 11 2026, 10:14 AM Please be advised that the dates of the works have been changed to 24-26 November. Original : November 10 2026, 3:20 PM As part of our Better Boating Plan, essential replacement works are being carried out at Kinver Customer Service Facility. The existing pump out equipment has become obsolete and our contractors will be installing a new pump unit. During the works, the pump out facility will be temporarily unavailable. The following facilities will remain open and available: * Elsan * Water points * Refuse, recycling and skip facilities The nearest alternative facility is Mart Lane (SW-001-083). We apologise for any inconvenience these works may cause and thank customers for their patience and understanding while this essential improvement is completed.